Tottenham Hotspur Football Club Stadium Pitch Replacement

October 2026

After the August 2026 renovation, the Tottenham Hotspur Stadium hosted a concert by Jay-Z in September, followed by two weeks of NFL events. During this time the retractable grass pitch stayed in storage for 23 days, so the club commissioned Fineturf and Tillers Turf to grow a completely new surface for installation once the events were over.

On Monday 12th October 2026, the existing surface was removed within a six-hour window. Laser grading and ground preparation followed straight away, and the Fineturf and Tillers Turf team began laying the new pitch in the early evening of the same day. The new turf came in on walking floor lorries, and the same vehicles then took the old pitch back to Fineturf to be repurposed. The surface was again grown on the Tillers-designed and manufactured hybrid carpet system, so the lift-and-lay process established at the stadium could be repeated with confidence on a tight programme.

The pitch was handed back to the club's grounds team on Thursday 15th October. Tottenham Hotspur played their first Premier League fixture on the new surface against Coventry City on Monday 19th October.

The project shows how quickly the Fineturf and Tillers Turf team can respond to the demands of a multi-use venue. A full playing surface was lifted, prepared and relaid in under four days, keeping the stadium ready for top-flight football between major events. Fineturf are proud to continue supporting Tottenham Hotspur Football Club and look forward to the partnership in the seasons ahead.

Client Projects