Scunthorpe United FC Main Pitch and Training Ground Renovation

Completed in
Share

Following the 2016-2017 football season we have completed the end of season renovation at Glanford Park. This years work included:

  • Fraise mow existing surface in two directions
  • Vacuum arisings
  • Spread sports sand
  • Disc seed Limagrain MM60
  • Drag mat
  • Apply 14:6:18 fertiliser

This year we also completed a drainage project at the clubs training facilities. Primary drainage was installed at 5m centres and gravel banding parallel to this at 0.75m centres.

Share

Project Specification

Completed
Machinery Blec Combinator, Wiedenmann Terra Spike, Sand Spreader, Trilo Vacuum, Vredo Disc Seeder