Manchester United The Cliff and Littleton Road

Completed in
Share

We have recently renovated two of Manchester United’s training facilities, the Cliff and Littleton Road.

At the Cliff the existing surface was removed and the pitches vacuumed. 90T of sports sand was spread. The pitches were aerated with 25mm solid tines and 13mm hollow tines. The sand was brushed in and Limagrain MM60 was sown in 5 directions with a disc seeder and 1 direction with a dimple seeder. A pre seeder fertiliser was also applied.

At Littleton Road the pitches were aerated with 20mm solid tines and cored using 13mm hollow tines. 360T of sports sand was spread and brushed in. Limagrain MM60 was sown in 4 directions with a disc seeder and 1 direction with a dimple seeder. A pre seeder fertiliser was also applied.

Share

Project Specification

Completed
Machinery Charterhouse Dimple Seeder, Dakota Turf Tender, Sand Spreader, Shelton Trencher Wheel, Trilo Vacuum, Vredo Disc Seeder
Materials Limagrain MM60 Seed